First Floor Platform
August 31, 2002: framing of the first floor platform began.
![]() |
![]() |
||
Bringing I-joists into place. | The very first nail. | ||
![]() |
![]() |
||
The first I-joist nailed in place! | Two I-joists in place before dinner. |
September 1, 2002: framing continued.
![]() |
![]() |
||
Putting glue in place for subfloor sheet. | The first subfloor sheet in place. |
![]() |
![]() |
![]() |
Screwing down the subfloor. | The first subfloor sheet complete. | End of day. |
September 2, 2002
![]() |
![]() |
||
Nearly all I-joists in place. | Looking over the work. |
September 3, 2002: platform framing completed.
![]() |
|
First floor platform framing complete. |
September 4, 2002: sheathing of the first floor platform continues.
![]() |
|
Floor sheating continues. Damp-proof membrane installed. |
September 8, 2002: first floor platform complete.
![]() |
![]() |
||
The first floor structure complete. | Finishing up. |