Drain and Concrete Work
April 8, 2003: Drain & Concrete contractor on site to attach sewer lines and lay drains in basement.
![]() |
![]() |
![]() |
||
Slinging extra stone into basement. | View from garage. | View from balcony. | ||
![]() |
![]() |
![]() |
||
View from sitting room. | Stone slung into basement. | Drain to stack for main bathroom and kitchen. | ||
![]() |
![]() |
![]() |
||
Furnace room floor drain (green),
stack for master bathroom (black) and water service. |
Back-filling. | |||
![]() |
April 9, 2003: Basement floor is poured.
![]() |
![]() |
![]() |
|||
Stone leveled before the pour. | |||||
![]() |
![]() |
![]() |
|||
Heater hung from ceiling. | Chute for concrete in place. | Concrete arrives. | |||
![]() |
![]() |
![]() |
|||
Screeding the concrete. | |||||
![]() |
![]() |
July 3, 2003: Porch and garage floor poured.
![]() |
![]() |
![]() |
||
![]() |
![]() |
![]() |
||
![]() |
![]() |
![]() |
||
Pad for air conditioner. | Posts for deck. | Pad for generator. |