Stucco
August 9, 2003: Stucco contractor just getting started.
![]() |
|
| Lower styrofoam installed. |
August 18, 2003: Stucco contractor setup and installed styrofoam base.
|
![]() |
![]() |
|
August 19, 2003: Styrofoam base being completed.
![]() |
![]() |
||
| Rear view. | |||
![]() |
![]() |
August 22, 2003: First coat applied to rear of house.
![]() |
|
August 26, 2003: First coat complete.
|
![]() |
![]() |
|
August 29, 2003: First colour coat.
![]() |
![]() |
||
| Rear view. | |||
August 30, 2003: Contractor applying finish coat on most of second floor.
|
![]() |
![]() |
|
| Working at the front of the house. | |||
![]() |
![]() |
||
| Working on the south side of the house. | |||
![]() |
![]() |
||
September 1, 2003: Final work being done.
|
![]() |
||
| Working at the front of the house. | |||
![]() |
![]() |
![]() |
|
| Taking down the scaffolding. | |||
September 2, 2003: Scaffold removal.
|
![]() |
||
| Some views of the finished stucco. | |||
![]() |
![]() |
![]() |
|