April 9, 2004: Framing begins.

Beam installation.

 
     

 

April 24, 2004: Decking underway - south retaining wall completed.

Final digging and adjusting for south retaining wall.

Trex™ decking being installed.

 

May 24, 2004: Gardening.

 
Preparing a vegetable garden.

 

 

June 3, 2004: Final grading and sod.

Clearing and leveling.
     
     
Gravel arrives. Sod arrives.
  Backyard graded. North side of house.
  Front lawn.
  Back yard. South side of house.
South side of driveway. The crew.

 

August 27, 2004: Sidewalk and driveway curbs.

 
     
     

 

October 4, 2004: Deck railings installed by CPL.

     

 